What is a fixed price contract?
A fixed price contract sets the scope, the price and usually the timeline before work starts. The vendor gets paid the agreed amount whether the work takes more or fewer hours than planned. The US federal procurement rules put it plainly: a firm-fixed-price contract has a price "not subject to any adjustment on the basis of the contractor's cost experience" and "places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss" (US Federal Acquisition Regulation, 2026). One of the conditions the same regulation lists for this model is that performance uncertainties "can be identified and reasonable estimates of their cost impact can be made" (US Federal Acquisition Regulation, 2026). For a software buyer, that is the condition that matters most.
To quote a fixed price honestly, a vendor needs written requirements, acceptance criteria for each feature, the integrations and environments named, and a clear definition of done. It also needs the non-functional requirements written down: performance targets, security testing, accessibility level, supported browsers and devices, data migration, and the tests and documentation handed over. Anything left out of the spec is the first thing a fixed price squeezes when the margin gets tight. Every unknown the vendor cannot pin down becomes a contingency inside the price. You do not see that buffer as a line item, and no published market figure tells you how large it typically is, so ask the vendor directly how they priced risk. Our custom software development page shows how an engagement is scoped in writing, and agreed by both sides, before build work begins.
What is a time and materials contract?
Time and materials (T&M) bills you for the hours or days the team actually works, at agreed rates, plus any pass-through costs such as licenses or cloud spend. Invoices go out weekly or monthly against timesheets. The federal rules describe T&M as labor hours "at specified fixed hourly rates that include wages, overhead, general and administrative expenses, and profit," used "when it is not possible at the time of placing the contract to estimate accurately the extent or duration of the work" (US Federal Acquisition Regulation, 2026).
Under T&M you control the backlog and the priorities. You can change direction after user feedback without renegotiating a contract. What you carry is the total cost: if the work takes longer, you pay for the extra time. The same regulation notes that T&M gives the supplier "no positive profit incentive" for cost control, which is why it requires active oversight. In commercial work, that oversight is your weekly burn report.
Ask for a rate card by role and seniority, and a named list of who will bill. Agree that replacing a team member needs your approval, and that onboarding hours for a replacement are not billed to you. Otherwise the rate stays fixed while the people behind it change.
Fixed price vs time and materials side by side
The table below compares the two textbook models with the two common hybrids; it is built from the standard contract definitions above, not from any vendor's project data.
Some large vendors list these as standard options. ScienceSoft, for example, offers "time and materials (T&M), time and materials (T&M) with a cap, fixed-price, subscription-based/per-ticket (for software support activities), or mixed model" (ScienceSoft, accessed 2026).
AI coding tools change the arithmetic too. Under time and materials, any speed-up shows up as fewer billed hours. Under fixed price, it stays with the vendor. Ask each vendor whether its estimate assumes AI-assisted development, how generated code is reviewed and tested, and how licensing of tool output is handled in the IP clause.
Time and materials with a cap: the middle ground
A capped T&M contract, also called not to exceed, bills hours as normal but writes a ceiling into the contract. The cap is only as useful as the clause that says what happens when you reach it. There are two versions in the market, and buyers often sign one while assuming the other. The labels "hard" and "soft" are used loosely, so read the clause, not the name.
- Cap with a completion obligation (often called a hard cap). The vendor commits to finish the agreed scope inside the ceiling and absorbs any hours past it. This term has to be written in. It is not what a ceiling means by default. Expect a vendor who accepts it to price the risk into its rates or the cap, much as it would for a fixed price.
- Spend ceiling only (often called a soft cap). Billing stops at the ceiling, and the vendor has no duty to keep working until you approve more budget. This is how US federal rules treat a time and materials ceiling: the government is not obliged to pay above it, and the contractor is not obliged to keep performing past it unless the ceiling is raised in writing (US Federal Acquisition Regulation, 2026).
A sound cap clause also sets a re-plan trigger well before the ceiling. US federal T&M contracts, for example, require the contractor to give notice and a revised estimate when costs are expected to pass 85 percent of the ceiling within the next 30 days (US Federal Acquisition Regulation, 2026). When burn crosses the agreed share of the cap, both sides meet, compare remaining scope with remaining budget, and agree in writing to cut scope, reorder it or extend the cap. No extension should be valid without written approval.
What a cap does not protect you from: reaching the ceiling with scope unfinished. A cap limits spend. It does not make an estimate right. That is why the next model exists.
Discovery first, then fixed price or capped T&M
A two-phase contract splits the work. First, a short paid discovery produces the inputs an honest quote needs: user flows, a prioritized backlog, architecture and integration decisions, the riskiest unknowns tested, and an estimate with stated assumptions. Then the build is priced on that output, either as a fixed price or as capped T&M.
Ask for the estimate as a range, a likely figure and a high figure, with the assumptions and the top risks listed next to it. A single number with no assumptions cannot be checked, and it gives you nothing to set a cap or a re-plan trigger against.
This is how fair fixed prices get made. A vendor quoting from a validated backlog can price closer to the real work, and you can compare two quotes line by line.
Two terms to check before you sign a discovery phase:
- You own the discovery outputs: documents, designs, backlog and any prototype code.
- You are free to take those outputs to another vendor without a penalty or a buyout fee.
If a vendor will not agree to both, treat the discovery as a sales cost, not a deliverable you own.
Which model fits your project?
The table below maps common buying situations to the model that usually fits; it reflects how risk moves under each contract type, not a statistical study.
A dedicated team is a third common model. You pay a monthly fee for a named team that works only on your product, and you direct the work. It suits long roadmaps where the team's accumulated knowledge is the asset; the trade-offs are covered on the dedicated development teams page.
Where the money goes: the same project under each model
This is an illustrative scope at market rates, not a CodeYep quote. The method: pick an hourly rate inside the published average agency rate band, then apply each model's mechanics. Clutch puts the average cost to hire a software development company at $25 to $49 per hour and the average project at $132,480 over about 13 months (Clutch, 2026). Techreviewer's survey of 127 providers found 37.8% billing $30 to $49 per hour (Techreviewer, 2026). Keyhole Software puts a simple or MVP build at $40,000 to $120,000 over 2 to 4 months (Keyhole Software, 2026). That range mixes rates, so treat the example below as an illustration, not a benchmark.
Assume an estimate of 2,000 hours at $40 per hour, a rate inside the Clutch average band (Clutch, 2026), which gives $80,000 of planned work. The mechanics hold at any rate. Then assume the agreed scope really takes 2,400 hours because the estimate was wrong, with no new features added. That is estimate risk, the scenario every buyer should price. New features users ask for are a separate cost: under every model, including a capped one, they are a change request or a cap extension.
The table below shows how that same 400-hour overrun lands under each model; the dollar figures are arithmetic on the assumptions above, not market data.
The point is not which row is cheapest. It is that fixed price makes you pay for risk whether or not it happens, while T&M makes you pay only for risk that does happen, with no ceiling unless you write one in. For the full picture of what drives a project's budget, read our guide to custom software development cost in 2026.
Change requests: the clause that decides your final bill
On a fixed price project, the change-request clause is where budget disputes usually surface. On a T&M project, the equivalent is how scope changes get approved and tracked. A fair process has five parts:
- A written request. Either side can raise it, and it describes the change in plain terms.
- A written impact. The vendor states the effect on cost, schedule and any acceptance criteria, before work begins.
- A pricing rule agreed in advance. The contract says which rate prices change requests, so the price of a change is not negotiated under pressure.
- Approval before work. Nothing is built on a change until a named person on your side approves it in writing.
- A running log. Every approved change is recorded, so the final invoice can be traced back.
Ask each vendor for a sample change request from their template and the clause that governs it, and compare those, not just the headline price.
Acceptance, warranty and dependencies
Three more clauses decide whether a fixed price stays fixed. First, an acceptance window: how many days you have to test each milestone, and what happens if you do not respond. Second, a warranty period: how long the vendor fixes defects against the agreed acceptance criteria at no charge, and a written line between a defect (it does not meet the spec) and a change (the spec was different). Third, a dependencies list: what you must supply and by when, such as feedback, test data, system access and third-party credentials, and how the schedule moves if a dependency is late. Tie milestone payments to acceptance, not to calendar dates.
Can agile work with a fixed price contract?
Yes: a fixed price per sprint, or a fixed budget with flexible scope where features trade in and out. Neither fixes the full feature list at the start.
How to read a time and materials invoice
A useful invoice lists hours by person, role, rate and feature, and matches the weekly burn report you already received. Ask before you pay any line you cannot trace to a person, a rate and a piece of work.
Red flags in either contract
- Fixed price with no acceptance criteria. Without them, "done" is whatever the vendor delivered, and every fix becomes a change request.
- A definition of change that includes clarifications. If answering a question about an existing requirement counts as new scope, the fixed price is not fixed.
- T&M with no weekly report. You should see hours burned against the estimate every week, by person and by feature, not only at invoice time.
- T&M with no view of the work itself. Timesheets show hours, not progress. Ask for a demo of working software every sprint and read access to the code repository, issue tracker and build pipeline from day one, so you can compare scope delivered against budget burned.
- Fixed price with no warranty or defect-fix period after acceptance. Ask how long defects are fixed at no charge.
- A cap with no re-plan trigger. You learn the budget is gone when the money is gone.
- A cap that does not say what happens at the ceiling. Read the clause for whether the vendor must finish the scope or may stop. If it is silent, ask.
- IP that transfers only at final payment. A payment dispute then leaves you without your own code. Ask for assignment per paid milestone and for repositories in your name; the security and IP practices page sets out what to look for.
- No notice period or exit terms. Every contract model needs a clause that says how either side ends it, how much notice applies, and what is handed over on exit.
The wider checks are in our guide on how to choose a software development company.
What to ask about caps, change requests and notice periods
Put these questions to every vendor on your shortlist, in writing, and compare the answers side by side:
- Caps. Do you offer capped T&M? Does the cap carry a completion obligation, or is it a spend ceiling only? At what share of the cap does a re-plan meeting happen, and who must approve an extension?
- Change requests. Which rate prices a change request? How fast do you return a written impact? Can I see a sample change request?
- Notice periods. How much notice does either side give to end the contract or reduce the team? What is billed during the notice period, and what is handed over at the end?
How CodeYep structures engagements
We offer three engagement models: fixed-scope projects, time and materials, and dedicated teams. Every engagement starts from a written scope that both sides agree before build work begins, so whichever model you choose, the work is tied to a document you can check. The contract assigns the code and intellectual property we write for you to you, and the source repositories and cloud accounts it lives in are set up in your name from the start. On request, we sign a mutual NDA before detailed project discussions.
Put the questions in the section above to us as you would to any vendor on your shortlist, and compare the answers. Our rates and engagement models page explains how each model is billed, and how a CodeYep engagement runs covers the steps from first call to handover. If you have a scope ready to discuss, discuss your project with us, or write to hello@codeyep.com.
How this guide was put together
Model definitions are industry standard and cross-checked against the US Federal Acquisition Regulation, which defines both contract types formally. Market figures come from Clutch, Keyhole Software and Techreviewer, and the list of standard pricing models from ScienceSoft, each dated in the text and listed in the sources with the date we opened them. The worked example uses those published ranges plus stated assumptions.